Head Brickwork, the contractor who do offer the full package in brickwork
 |
Client:Gleeson Build
Value:£1 Million.
Location:Oasis Academy, Immingham
Description:New School
Duration:30 Weeks
Completion:01/09/2008
|
 |
Client:Carillion PLC
Value:£500, 000
Location:The Square Project, Sheffield
Description:New Offices
Duration:16 Weeks
Completion:01/07/2008
|
 |
Client:Balfour Beatty Construction
Value:£500, 000
Location:Fire Station, Sheffield
Description:New Fire Station
Duration:20 Weeks
Completion:01/05/2008
|
 |
Client:Harrisons Construction
Value:£450, 000
Location:Cross Bedford Street Peninsula, Sheffield
Description:New Flats Development
Duration:18 Weeks
Completion:01/04/2008
|
 |
Client:Norwest Holt
Value:£650, 000
Location:Edlington School, Doncaster
Description:New School
Duration:30 Weeks
Completion:01/09/2008
|
 |
Client:Clegg Construction
Value:£650, 000
Location:Edward Street, Sheffield
Description:Residential Appartments & Student Accomodation
Duration:24 Weeks
Completion:02/12/2008
|
 |
Client:HBG Construction Ltd
Value:£500, 000
Location:Bradford College, Bradford
Description:New College Building
Duration:20 Weeks
Completion:01/02/2008
|
 |
Client: Bluestone Plc
Value:£150, 000
Location:Moorlands school, Huddersfield
Description:New School
Duration:10 Weeks
Completion:17/09/2007
|
 |
Client: Bluestone Plc
Value:£135, 000
Location:Castle college, Nottingham
Description:New College Building
Duration:12 Weeks
Completion: 17/09/2007
|
 |
Client: Wilson Bowden Developments PLC
Value:£250, 000
Location:Units G,J,K Ivanhoe business Park, Ashby
Description:Commercial Premises
Duration:18 Weeks
Completion:01/11/2007
|
 |
Client: Kier Northern
Value:£150,000
Location:York Hospital, York.
Description:New Build And Refurbishment
Duration:15 Weeks
Completion:01/09/09
|
 |
Client: Morgan Ashurst
Value:£200,000
Location:Deb HQ, Derby
Description:New Head Quarters and Units
Duration:18 weeks
Completion:01/07/09
|
 |
Client: Morgan Ashurst
Value:£150,000
Location:Stile Common, Huddersfield
Description:New Primary School
Duration:12 weeks
Completion:08/08/09
|
 |
Client: Kier Marriot
Value:£450,000
Location:Samworth Academy, Mansfield
Description:New School
Duration:22 Weeks
Completion:01/10/09
|
|
|
|